How the BIF Act works in Queensland

The short version

If you've done construction work, or supplied related goods or services, under a contract for a job in Queensland and you haven't been paid, the Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act) gives you a fast, fixed-deadline way to get a decision on what you're owed, without going to court.

It works in three steps. You give the other side a payment claim. They have 15 business days to pay or to give you a payment schedule saying what they'll pay and why. If they pay less than you claimed, or pay nothing, you apply to the Adjudication Registry at the QBCC and an adjudicator decides the amount, usually within a few weeks. The decision is enforceable as a court judgment.

The catch is the deadlines. Every step has one, they are counted in Queensland business days, and if you miss one the claim fails. That is the whole reason to get the paperwork right the first time.

Who the BIF Act covers

The Act applies to construction contracts for construction work, or the supply of related goods and services, carried out in Queensland (s 61). A "contract" can be written, oral, or a mix of both, so a quote accepted by text message counts. It covers:

  • subcontractors claiming against head contractors
  • head contractors claiming against principals and developers
  • suppliers of materials, plant and labour hire
  • consultants such as architects, engineers, surveyors and project managers.

It doesn't matter how big the job is. Claims under the Act range from a few thousand dollars to tens of millions.

One Queensland-specific point to check before you start: the Act doesn't cover domestic building work for a resident owner, that is, a home owner who lives or intends to live in the building (s 61(2)(b)). Owner-builders and building contractors don't count as resident owners, so work for them is still covered. If you're not sure which side of the line your customer is on, call us and we'll check.

Step 1: the payment claim

You are entitled to a progress payment on each reference date under your contract (s 70). The reference date is the date your contract names for making a claim. If the contract is silent, it's the last day of each month in which you did the work, and after termination it's the day the contract ended (s 67).

A payment claim is a written document that identifies the work, states the amount claimed and asks for payment (s 68). In Queensland your ordinary invoice can be a payment claim; it no longer has to say it's made under the Act. The claim must be given:

  • within 6 months after you last carried out the work or supplied the goods, or a longer period if your contract allows one (s 75(2)), and
  • for your final claim, within the longest of the contract's period, 28 days after the end of the last defects liability period, or 6 months after completion of all the work (s 75(3)).

Only one payment claim can be made for each reference date (s 75(4)), but you can include amounts from earlier claims that are still unpaid (s 75(5)).

Head contractors: a payment claim given to the principal must be accompanied by a supporting statement declaring that all subcontractors have been paid what is due, or listing the ones that haven't and why (s 75(7)). Leaving it out is an offence (maximum 100 penalty units), though it doesn't invalidate the claim (s 75(8)).

Step 2: the payment schedule

Once the claim is given, the respondent has 15 business days, or less if the contract says so, to respond with a payment schedule (s 76). The schedule must identify the claim, state the amount they propose to pay, and if that's less than you claimed, say why (s 69).

If they don't give a schedule in time, they become liable for the full amount claimed on the due date for payment (s 77), and they lose the right to put any reasons for non-payment to an adjudicator later (s 82(2)).

The due date for payment is the date your contract sets, or 10 business days after the claim is given if it says nothing (s 73). Queensland caps contract payment terms: a commercial building contract can't make you wait more than 15 business days, and a construction management trade contract or subcontract more than 25 business days; anything longer is void (QBCC Act ss 67U, 67W). "Pay when paid" clauses have no effect (s 74).

Step 3: adjudication

If the schedule is for less than you claimed, if the scheduled amount isn't paid, or if no schedule arrives and you're not paid, you can apply for adjudication (s 79). The deadlines are:

SituationYou must apply within
Schedule given for less than you claimed30 business days after you received the schedule
Schedule given but the scheduled amount not paid20 business days after the due date for payment
No schedule and no payment30 business days after the later of the due date for payment and the day the schedule was due

Queensland has no "second notice" step; you apply directly. The application goes to the Adjudication Registry at the Queensland Building and Construction Commission with the fee, and a copy must be given to the respondent (s 79). The Registrar refers it to an adjudicator within 4 business days (s 81).

The respondent can lodge an adjudication response within 10 business days after receiving the application, or 7 business days after notice of the adjudicator's acceptance, whichever is later; 15 and 12 business days for a complex claim, which is one over $750,000 (s 83). The response can't raise reasons that weren't in the payment schedule, and the adjudicator can send it back to have them removed (s 82(4)–(5)). A respondent who didn't give a schedule can't respond at all (s 82(2)).

The adjudicator decides within 10 business days of the response date (15 for complex claims), and can ask both sides to agree to more time (s 85). The decision states the amount payable, the date it was due, the interest rate, and who pays the adjudicator's fees (s 88).

Getting paid after the decision

The respondent must pay within 5 business days of receiving the decision, or by the due date if later (s 90).

If they don't, the Registrar issues an adjudication certificate within 5 business days of the decision (s 91) and you file it in court, with an affidavit that it hasn't been paid, as a judgment debt (s 93). From there it's an ordinary enforcement: garnishee of a bank account or debtors, a warrant on assets, or a statutory demand. You can also give notice and, 2 business days later, suspend work until you're paid (ss 92, 98).

An adjudication decision is interim: either side can still take the underlying dispute to court or arbitration later, but the money changes hands now. In practice most decided claims are the end of the matter.

Business days in Queensland

Business days exclude Saturdays, Sundays, public holidays, and 22 to 24 December, 27 to 31 December and 2 to 10 January (sch 2). With Christmas Day, Boxing Day and New Year's Day being public holidays, that means nothing counts from 22 December to 10 January. A claim given on 20 December therefore has a very different timetable from one given on 20 November. We count every deadline for you.

What we do

We prepare and serve payment claims, check your contract for reference dates and payment terms, prepare and lodge adjudication applications, and run the enforcement if the decision isn't paid. We've been doing this for Queensland contractors since the days of the old 2004 Act, and 98% of our claims succeed at adjudication. We're a licensed commercial agent, not a law firm, and we're not connected with the QBCC.

This page is a simplified guide to the Building Industry Fairness (Security of Payment) Act 2017 (Qld), last reviewed October 2026. It isn't legal advice.