Payment schedules under the BIF Act: the 15-business-day reply

What a payment schedule is

A payment schedule is the respondent's written answer to a payment claim. Under s 69 of the BIF Act it must:

  1. identify the payment claim it responds to;
  2. state the amount, if any, the respondent proposes to pay; and
  3. if that amount is less than the amount claimed, say why, including the reasons for withholding any payment.

That third point is the one that decides most disputes. Whatever reasons the respondent puts in the schedule are the only reasons they can run at adjudication. Anything left out is lost (s 82(4)). A schedule that just says "disputed" or "not approved" has stated a reason in form only, and adjudicators treat it that way.

The Act doesn't prescribe a form. A letter, an email or a marked-up copy of the claim can all be a payment schedule, as long as they do the three things above.

The deadline

The respondent must give the schedule within 15 business days after the payment claim is given, or within any shorter period the contract sets (s 76(1)). The contract can shorten the period; it can't lengthen it.

Queensland counts business days strictly: no weekends, no public holidays, and nothing between 22 December and 10 January. A claim given on 10 December gives the respondent until well into January, which is why the timing of year-end claims matters so much to both sides.

There's no need to give a schedule if the claim is paid in full by the due date for payment (s 76(2)). Paying in full is the only way out of the obligation.

If no schedule is given

Not giving a schedule in time has three consequences for the respondent:

  • they become liable to pay the full claimed amount on the due date for payment (s 77);
  • they can't give an adjudication response at all, so the adjudicator decides on the claimant's material alone (s 82(2)); and
  • they commit an offence carrying a maximum penalty of 100 penalty units, and the failure is a ground for QBCC disciplinary action (s 76(1)).

The third point is particular to Queensland. In most other states ignoring a claim is merely expensive; here it's also a licensing problem.

For the claimant, no schedule means you can apply for adjudication within 30 business days after the later of the due date for payment and the last day the schedule could have been given (s 79(2)(c)), or sue for the amount as a debt (s 78). You don't have to give any further notice first.

If a schedule is given

If the schedule proposes to pay less than the claim, you have 30 business days after receiving it to apply for adjudication (s 79(2)(a)). If it proposes an amount and that amount isn't paid by the due date, you have 20 business days after the due date to apply (s 79(2)(b)). The respondent must pay the scheduled amount by the due date whether or not you go to adjudication; not paying it is itself an offence (s 76(3)).

The due date for payment is the one in your contract, or 10 business days after the claim if the contract is silent, and Queensland caps contract terms at 15 business days for commercial building contracts and 25 for construction management trade contracts and subcontracts (s 73; QBCC Act ss 67U, 67W).

One exception on the respondent's side: a respondent who has been served a payment withholding request under chapter 3, part 4A can retain the amount it covers out of the scheduled payment (s 76(4)).

Reading a payment schedule

When a schedule arrives we go through it line by line against the claim, because the gaps are where adjudications are won. We're looking for:

  • amounts "not yet assessed" or "pending" (not a reason; that money is usually recoverable in full)
  • back-charges and set-offs with no supporting figures or notice under the contract
  • defect claims that were never raised before the schedule
  • "pay when paid" reasoning, which the Act makes void (s 74)
  • reasons that contradict the respondent's own earlier correspondence or site records.

Each of these becomes a submission in the adjudication application. The respondent is stuck with what they wrote.

If you've received a payment claim

The Act applies to you as much as to the claimant, and the clock is already running. Within 15 business days you need to either pay in full or give a schedule that sets out every reason you have for paying less, with the numbers. Reasons you don't include now can't be used later.

We act for respondents as well as claimants. If you've received a payment claim, send it to us straight away and we'll prepare a payment schedule that puts every legitimate reason on the record, in time, and then run the adjudication response if the claimant applies. A schedule done properly in the first 15 business days is worth more than any amount of argument afterwards.

This page is a simplified guide to chapter 3 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), last reviewed October 2026. It isn't legal advice.