The BIF Act process at a glance: Queensland flowchart
Every step in a Queensland security of payment claim, from the payment claim to an enforceable judgment, with the business-day limits that apply at each one. Section references are to the Building Industry Fairness (Security of Payment) Act 2017 (Qld).
Claimant actsRespondent actsRegistry / adjudicatorOutcomeBD = Queensland business days
1. Claimss 67, 68, 70, 75
Reference date arrivesThe date the contract sets for a progress claim; otherwise the last day of each month in which work was done, and the termination date if the contract ends.
▼
Claimant gives the payment claim within 6 months of the workIn writing, identifying the work and stating the amount; an invoice can be the claim. Given to the party liable under the contract. One claim per reference date; earlier unpaid amounts can be included. Head contractors attach a supporting statement.
▼
2. Responsess 69, 73, 76, 77
Respondent has 15 BD (or a shorter contract period) to do one of three things
pays in fullgives a scheduledoes nothing
Pays the claim in full by the due dateNo schedule needed. Matter closed.Due date: as the contract says, else 10 BD after the claim (s 73); contract terms capped at 15 or 25 BD.
Gives a payment scheduleMust identify the claim, state the amount it will pay and, if less, every reason why. Those reasons are the only ones it can ever argue (s 82(4)).Must pay the scheduled amount by the due date (s 76(3)).
Gives no schedule in timeLiable for the full claimed amount on the due date (s 77). Can't give an adjudication response at all (s 82(2)). Offence: up to 100 penalty units.
▼
3. Claimant's choicess 78, 79
If not paid in full by the due date, the claimant may apply for adjudication, or sue for the amount as a debt, and may give 2 BD notice of intention to suspend workNo second notice or warning step. The adjudication deadline depends on what the respondent did:
▼
Schedule for less than claimedApply within 30 BD after receiving the schedule.
Schedule given, scheduled amount not paidApply within 20 BD after the due date for payment.
No schedule and no paymentApply within 30 BD after the later of the due date and the last day a schedule could have been given.
▼
4. Applicationss 79, 81; regs 15–17
Claimant lodges the application with the QBCC Adjudication RegistryApproved form, fee, submissions and evidence. Lodge by 5pm on a business day. Claims of $25,000 or less: submissions capped at 10 pages.Claimant gives the respondent a copy within 4 BD of lodging.
▼
Registrar refers it to an adjudicator within 4 BDClaims over $150,000 go to a more senior adjudicator.
Adjudicator accepts or rejects within 4 BDWritten notice of acceptance to both parties. If rejected, re-referred at no further fee.
▼
5. Adjudication responsess 82, 83
Respondent that gave a schedule may respondWithin the later of 10 BD after receiving the application and 7 BD after notice of acceptance. Complex claims (over $750,000): 15 and 12 BD, with up to 15 more on request.No new reasons beyond the payment schedule. Copy to the claimant within 2 BD.
Respondent that gave no scheduleNo response permitted. The adjudicator decides on the claimant's material.
▼
6. Decisionss 84–88, 94–96
Adjudicator decides within 10 BD after the response date (15 BD for complex claims)Considers only the Act, the contract, the claim and schedule with their submissions, and any inspection. May request further submissions, call an informal conference or inspect the work. Decides the adjudicated amount, the date it was payable, the interest rate, and how the adjudicator's fees and the application fee are split.Parties can agree in writing to extend. If the adjudicator misses the deadline, the claimant has 5 BD to ask for re-referral or apply again.
▼
7. Paymentss 90–93, 98
Respondent must pay the adjudicated amount within 5 BD of receiving the decisionOr by any later date the adjudicator sets. Not paying is an offence (up to 200 penalty units).
paidnot paid
PaidMatter closed. The decision is interim; either side may still take the underlying dispute to court or arbitration, but in practice few do.
Not paidRegistrar issues an adjudication certificate within 5 BD of the decision. Claimant files it in court with an affidavit of non-payment and it becomes a judgment debt. Then garnishee, enforcement warrant or statutory demand. Claimant may also suspend work on 2 BD notice.
Reading the chart
- Business days exclude weekends, Queensland public holidays and 22 December to 10 January (sch 2). Count them, don't estimate them.
- Every limit on the claimant's side is a hard limit: a day late and the application can't be accepted. The way back is a fresh payment claim on the next reference date, with the unpaid amount included (s 75(5)).
- The respondent's payment schedule is the hinge of the whole process. What it says, and whether it was given in time, determines what the respondent can argue at step 5 and usually who pays the costs at step 6.
- The chart is for a standard claim. Complex claims (over $750,000) have the longer response and decision periods shown. Domestic building work for a resident owner is outside the Act altogether (s 61(2)(b)).
Where you are on the chart
If you're at step 1 or 2 as a claimant, start with a payment claim. If you're at step 3 or later, the adjudication form is the one to use. If you're the respondent at step 2 or 5, call us: the periods are short and nothing left out of the schedule can be added later.
This chart is a simplified guide to chapter 3 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) and the Building Industry Fairness (Security of Payment) Regulation 2018, last reviewed October 2026. It isn't legal advice.