Payment claims under the BIF Act: how to get yours right

The payment claim is where most claims are won or lost

Everything that follows under the BIF Act, the 15-business-day schedule deadline, the adjudication, the enforceable decision, hangs off one document: the payment claim. If it's given at the right time, to the right person, with the right content, the respondent is boxed in from day one. If it isn't, the adjudicator may have no jurisdiction and you start again a month later. This page is about getting it right.

What a payment claim is

Under s 68 of the Act a payment claim is a written document that:

  1. identifies the construction work, or the related goods and services, it covers;
  2. states the amount you claim is payable (the claimed amount); and
  3. requests payment of that amount.

(The Act also allows the regulation to prescribe extra content, but it currently prescribes none.)

Any written document bearing the word "invoice" is taken to request payment (s 68(3)). In practice that means your normal tax invoice can be a payment claim under the Act, as long as it identifies the work and states the amount. Unlike the old 2004 Act, and unlike NSW, Queensland no longer requires the words "made under the Building Industry Fairness (Security of Payment) Act 2017" on the document. You can still put them on; it does no harm and makes your intention plain.

The claimed amount can include retention money you say is due for release, and amounts the respondent owes you for a lawful suspension of work (s 68(2)).

When you can make one: reference dates

You get one payment claim per reference date (s 75(4)). The reference date is whatever your contract names as the day you can claim a progress payment (s 67(1)(a)). If the contract is silent, it's the last day of the month in which you first did work under the contract, and the last day of each month after that (s 67(1)(b)).

If the contract is terminated and it either says nothing about reference dates after termination or tries to stop them, the termination date becomes your final reference date (s 67(2)). That final date matters: it's often the only way to claim for the last stretch of work on a job that ended badly.

Because a claim can only be made on or after a reference date, a claim dated the 28th for work done that month under a silent contract is premature; wait for the last day of the month. We check this on every claim before it goes out.

When it's too late

A payment claim must be given within the longest of your contract's claim period and 6 months after you last did the work or supplied the goods it relates to (s 75(2)). For the final claim on a job the window is the longest of the contract period, 28 days after the end of the last defects liability period, or 6 months after completion of all the work (s 75(3)).

Those are the outside limits. There's no advantage in using them. The further you are from the work, the harder it is to prove, and every month of delay is a month the respondent's cash is moving elsewhere.

Including earlier amounts

A payment claim can include amounts that were in a previous claim (s 75(5)). So if an earlier invoice was ignored and the adjudication deadline on it has passed, you can roll the unpaid amount into the claim for the next reference date and start the clock again. This is one of the most useful features of the Queensland Act and one of the least used.

Head contractors: the supporting statement

If you're a head contractor claiming against the principal and you have subcontractors on the job, your payment claim must be accompanied by a supporting statement (s 75(7)). It either declares that all subcontractors have been paid everything owed to them at the date of the claim, or lists each one who hasn't, with the amount unpaid, the details of their claim, when they did the work, and why they haven't been paid in full (s 75(9)).

Giving a claim without it is an offence with a maximum penalty of 100 penalty units, although the claim itself stays valid (s 75(8)).

Giving the claim

The claim must be given to the person who is, or may be, liable to pay under the contract (s 75(1)): the party you contracted with, not the site manager, the project's developer or the person who happens to pay the bills. Get the legal entity right; an ABN check takes a minute.

It can be given in any way the contract allows, including email if the contract says so, and otherwise by the usual methods for giving notices (s 102). Keep proof: the sent email with its attachment, the courier docket, a file note of hand delivery with the date and time. The respondent's deadlines run from the day the claim is given, so the date has to be provable.

What happens next

The respondent has 15 business days, or any shorter period in the contract, to give you a payment schedule (s 76(1)). In Queensland that's not optional: failing to give a schedule is an offence carrying 100 penalty units and is grounds for QBCC disciplinary action (s 76). If they pay the claim in full by the due date they don't need to give one (s 76(2)).

If no schedule arrives, the respondent becomes liable for the whole claimed amount on the due date for payment (s 77), and loses the right to argue against the claim at adjudication. If the schedule proposes a lower amount, they must pay at least that amount by the due date (s 76(3)).

If you're not paid in full by the due date, the Act gives you a choice: sue for the amount as a debt in court, or apply for adjudication (s 78(2)). Adjudication is the route we use in almost every case. It's faster, it's cheaper, the deadlines force the respondent's hand, and a respondent who gave no schedule can't even argue. Court is for the rare case where the respondent has no defence and no intention of turning up. Either way, you can also give notice of your intention to suspend work (s 78(3)).

A pre-flight checklist

Before a claim leaves our office it has been checked for:

  • the correct respondent entity and ABN
  • a reference date that has arrived
  • the claim being inside the 6-month (or final-claim) window
  • a clear description of the work, period and site
  • the claimed amount, with GST, and how it was calculated
  • variations, retentions and suspension costs identified separately
  • a supporting statement, if you're a head contractor
  • a provable method and date of giving.

This page is a simplified guide to chapter 3 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), last reviewed October 2026. It isn't legal advice.