You've won at adjudication, the 5 business days have passed, and the respondent hasn't paid. You can file the certificate as a judgment and enforce it, but a respondent with no money in its own account is slow to collect from. What it usually does have is money coming to it from the party above it on the job. Since October 2020, the BIF Act lets you reach that money directly.
A payment withholding request (PWR) is a notice, in the QBCC's approved form, that requires the party who owes the respondent money for the same work (the "higher party") to hold back enough of it to cover your adjudicated amount (s 97B). It is Queensland's version of a tool that has existed in New South Wales since 2011, and it is one of the few things a claimant can do after adjudication that doesn't involve a court.
Two conditions (s 97B(1)):
You don't need to have filed the adjudication certificate first, and giving a PWR doesn't stop you doing anything else to enforce the decision at the same time (s 97H).
| If you are | The higher party is |
|---|---|
| A subcontractor (or supplier or consultant engaged by a contractor) | Whoever owes, or will owe, the respondent money under an arrangement for the same work: usually the head contractor, or the principal if the respondent is the head contractor |
| The head contractor | The financier for the work: the bank or other lender funding the project (s 97A) |
One exclusion: a PWR can't be given to a higher party who is a resident owner, that is, a home owner having domestic building work done on their own home (s 97B(2A)).
You may not know who sits above the respondent, or whether anything is still owed to it. The Act deals with that. You can require the respondent to tell you, within 5 business days, the name and business address of the higher party and whether any amount is or will become payable to the respondent for the work (s 97F). Not answering is an offence (20 penalty units); answering falsely is a worse one (100 penalty units). We send this request on the day the s 90 period expires, because the answer decides what happens next.
Once it receives the PWR, the higher party must retain, out of what it owes the respondent for the work, the adjudicated amount or the amount it owes, whichever is less (s 97C(2)). The Act's own example: if the adjudicated amount is $55,000 and the higher party owes the respondent $40,000, it retains $40,000; if it owes $120,000, it retains $55,000. The obligation lasts until you're paid, and shrinks with any part payment (s 97C(3)–(4)).
The higher party is protected while it complies: retaining the money is a complete defence if the respondent tries to recover it, and the period of retention doesn't count against the higher party as late payment (s 97E). If the person you've served isn't in fact a higher party (for example, because it had already paid the respondent out in full before the request arrived), it must tell you so within 5 business days (s 97B(5)).
If the higher party pays the respondent anyway, it becomes jointly and severally liable with the respondent for your adjudicated amount, to the extent of what it should have retained (s 97D). You can then recover that amount from the higher party, which usually has deeper pockets and more to lose from a QBCC complaint, and it is left to recover it from the respondent itself.
The retained amount is also subject to a statutory charge in your favour, which you can enforce as if the higher party had granted it to you by written agreement, and anything done to defeat the charge is of no effect against you (s 97G).
A PWR freezes the money; it doesn't by itself move it to you. The retained amount comes to you when the respondent pays (often prompted by the higher party, which now has every reason to lean on it), or when you enforce: file the adjudication certificate as a judgment (s 93), then garnishee the retained amount in the higher party's hands, or enforce the s 97G charge. We run the PWR and the enforcement together so the two arrive in the right order.
A head contractor with an unpaid adjudicated amount has a second tool. Once you've filed the adjudication certificate as a judgment, and if the respondent or a related entity owns the land the work was done on, you can lodge a request with the Titles Registry to register a charge over that land, with the certificate and a statutory declaration (s 100B). The charge lasts 24 months and a court can extend it for up to 24 more (s 100C). A developer that wants to sell, refinance or settle lots has to deal with you first.
From the day the adjudicated amount falls due unpaid we send the s 97F information request, identify the higher party, prepare and give the PWR in the approved form with the copy to the respondent, deal with any "not a higher party" response, and run the certificate, judgment and garnishee or charge alongside it. For head contractors we also prepare the Titles Registry request for the charge over property.
If you have an adjudication decision that hasn't been paid, call us now rather than waiting out the judgment process. Money that is still owed to the respondent today may have been paid out by next week.
This page is a simplified guide to chapter 3, parts 4A and 4B of the Building Industry Fairness (Security of Payment) Act 2017 (Qld), last reviewed October 2026. It isn't legal advice.