Queensland has had security of payment legislation for more than twenty years, but the rules a contractor works under today are quite different from the ones the industry learned in 2004. This is a short account of how the law got to where it is, and what each change means for anyone chasing a progress payment now.
The Building and Construction Industry Payments Act 2004 (BCIPA) commenced on 1 October 2004, modelled on the New South Wales Act of 1999. It introduced the structure that still applies: a payment claim, a payment schedule from the respondent, and a fast adjudication by an independent adjudicator whose decision could be enforced as a judgment. Under BCIPA a payment claim had to state that it was made under the Act, the respondent had 10 business days to give a payment schedule, and if no schedule arrived the claimant had to give a second notice (under s 21(2)) and wait a further 5 business days before applying for adjudication. Applications went to private authorised nominating authorities (ANAs), which chose the adjudicator.
A 2013 review by Andrew Wallace, then a barrister and later a federal MP, led to the Building and Construction Industry Payments Amendment Act 2014, which commenced on 15 December 2014. It abolished the ANAs’ role in appointing adjudicators and created the Adjudication Registry at the Queensland Building and Construction Commission, which has received every Queensland application since. It also split claims into “standard” and “complex” (over $750,000), gave respondents to complex claims longer to respond and let them raise new reasons that weren’t in the payment schedule, and shortened the time for giving a payment claim from 12 months to 6 months after the work. Many in the subcontracting sector saw the 2014 changes as tilting the Act towards respondents.
The Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act) was passed in late 2017 as part of a broader package that also introduced project bank accounts (now project trust accounts). Its security of payment chapter commenced on 17 December 2018 and repealed BCIPA. For claimants the practical changes were:
Later amendments, commencing in stages from 2020, replaced project bank accounts with project trust accounts and retention trust accounts, phased in by contract value, and added two tools for claimants who have an adjudicated amount they can’t collect: a payment withholding request, which requires the party above the respondent in the contracting chain to hold back money owed to the respondent (chapter 3, part 4A), and a statutory charge over the property on which the work was done (chapter 3, part 4B). Both are covered in our payment withholding requests guide.
The BIF Act is, on balance, a claimant’s Act. The deadlines are fixed and short, the respondent’s case is locked in at the payment schedule stage, and a respondent that doesn’t engage loses the right to argue at all. The price of that advantage is precision: a claim given on the wrong date, to the wrong entity, or outside the 6-month limit gives the adjudicator nothing to decide. That is the work we do, and have done for Queensland contractors under both Acts.
For a step-by-step guide to the current process, see how the BIF Act works or the BIF Act flowchart. If you have an unpaid Queensland invoice now, start a claim or call 1300 732 687.
Last reviewed October 2026. This article is general information, not legal advice.